Pemag Makina
Silivri, Istanbul
2020
Industrial
This facility for Pemag Machinery is precisely engineered to meet the specialist infrastructure demands of heavy machine manufacturing. A double-reinforced raft foundation, 10-tonne overhead crane system and hardener-additive industrial floor slab are the defining structural features of this project.
Project Challenges
Dynamic loads transmitted to the floor by CNC machine tools and industrial presses made standard reinforced-concrete slab solutions inadequate. An overhead crane beam integrated into the steel columns was also required for the 10-tonne bridge crane, and floor wear resistance had to meet industry specification.
Our Solutions
Based on ground investigation findings, a 300 mm thick double-reinforced raft foundation was designed. An overhead crane beam system integrated into the steel columns provided 10-tonne lifting capacity; the floor surface was finished with hardener-additive concrete achieving 4 N/mm² wear resistance.
Driven by our love for people and the environment and respect for our craft, we have been providing architectural and contracting services since 2010.